RV-12 Build Log

 

39.11-6 step 8 11-08 step 11 11-08 steps 1-7 inventory fuselage kit 12.5 5/17/2016 12.5
40.11-05 step4 10 5/19/2016 10.0
41.11-08 step9-11 12-01 step1 10.1 5/21/2016 10.0
42.12-02 -04 step 3 11.5 5/24/2016 11.5
43.inventory continued of fuselage 20-02 rivet nut plates 6 5/26/2016 6.0
44.remake several errors on tail section.Tailcone Inspection 7 5/31/2016 7.0
45.pg.20-03 steps 1-3 7.5 6/2/2016 7.5
46.pg20-3 step4 pg 20-4 steps 8-12 12.5 6/7/2016 12.5
47. inspect condition of F1204D to center section. Pg20 step 5 pg 21 steps 2-9 12.5 6/9/2016 12.5
48.pg21-02 step2 11 6/10/2016 11.0
49.pg21-02 step 2-4 riveting 8.5 6/11/2016 8.5
50.pg21-02 step5 pg21-03 step7 7.5 6/14/2016 7.5
51.pg21-02 steps12-14 steps 5,9,11 13.5 6/21/2016 13.5
52.pg21-02 step8 pg21-03 step 5 5 6/23/2016 5.0
53.pg21-02 step8 pg21-03 step 5 pg 21-04 step3 6 6/25/2016 6.0
54.pg21-04 step2 pg 21-05 step7 11 6/27/2016 11.0
55.pg21-05 deburr, 2104 21-05 deburring 22 6/28/2016 22.0
56.pg21-05 steps9-12 pg sec 30-2 steps 1-3 12 6/30/2016 12.0
57.sec39 steps 4-6 pg 21-05 step13 pg 21-06 steps 1-4 8 7/2/2016 8.0
58.pg12-06 step7 pg21-08 step4 8.5 7/5/2016 8.5
59.pg21-08 step 5 pg21-09 steps1-2 14 7/7/2016 14.0
60.pg21-10 steps1-2 3 7/8/2016 3.0
61.pg21-10 steps 3-6 4 7/9/2016 4.0
62.pg21-10 steps 7-10 pg21-11 step1-3 11 7/12/2016 11.0
63.pg21-11 step4 pg21-13 step2 11.5 7/14/2016 11.5
64.pg21-13 steps 3-4 6 7/16/2016 6.0
65.pg21-13 step3 pg21-14 step6 12.5 7/19/2016 12.5
66.pg21-15 steps 2-8 7.5 7/21/2016 7.5
67.pg21-16 steps1-3 6 7/26/2016 6.0
68.pg21-16 step7 pg21-17 step1 9 7/28/2016 9.0
69.pg21-17 steps1-2 3 7/30/2016 3.0
70.pg21-17 steps3-5 pg21-19 steps1-2,5-8 sec39-312 39-04-04 12 8/2/2016 12.0
Total hours  678.3 678.3